Corrective Actions
Corrective Actions are the paper trail our system provides to track problems from their discovery in an inspection to responsible parties tasked with correcting them.
Last updated
Corrective Actions are the paper trail our system provides to track problems from their discovery in an inspection to responsible parties tasked with correcting them.
Last updated
From the Main Page, navigate to “Corrective Actions” from the left navigation menu.
There are different ways for the user to find the corrective actions for them to address.
On the Open Action tab, the contractor can see all corrective actions at a glance assigned to them. The information provided from this page are:
Due date for the Corrective Action
The person the corrective actions were assigned to
The date the inspection was done that generated the corrective action
The space that was inspected
The inspector that conducted the inspection
Notes the inspector included with the corrective Action
By clicking on the expand arrow, additional details can be viewed for that specific Corrective Action.
Due date for the Corrective Action
Date of the Inspection
Number of corrective actions in this inspection
The Type of inspection that was carried out
The space that was inspected
The Inspector that inspected the project